Agora, Oud Gastel, Niederlande

  • Gebäudeart:
  • Lager & Logistik
Vollbild Schliessen Street View

Peikko Benelux delivered HPKM® Colum Shoes and HPM® Anchor Bolts for the construction of the new distribution centre of Agora 21B. The hundreds of concrete columns were divided into four phases and erected very quickly thanks to Peikko's innovative bolted columns connections. A significant amount of hours of manpower and crane hours have been saved as a result of this choice. Please have a look at the timelapse video on this page.

Projektdaten

Nutzfläche:
48.900 m2
Projektentwickler:
Heylen Group
Bauunternehmen:
Willy Naessens Nederland
Tragwerksplanung:
Willy Naessens Nederland
Fertigteilwerk:
Willy Naessens Industriebouw
Lieferzeitraum:
2016
Fertigstellung:
2017

Kontakt